METHOD FOR SELECTING A COST-EFFECTIVE OPTION OF THE SEQUENCE OF CONSTRUCTION OF BUILDINGS AND STRUCTURES IN A COMPLEX
DOI:
https://doi.org/10.36773/1818-1112-2021-126-3-103-107Keywords:
pre-design stage, construction organization project, complex of buildings and structures, construction phase, sequence of construction, financing schedule, discounted costsAbstract
When developing a justification for investment in the construction of facilities in accordance with regulatory documents, alternative studies and calculations should be carried out in order to determine the effectiveness of investments.
This article offers a method for assessing the economic efficiency of options for the sequence of construction of a complex of buildings and structures. The method is based on the income approach (the net income generated by the complex of facilities is calculated) and on the cash flows discounting. At the same time, the economic effects for the investor are taken into account: effects from the reduction of discounted costs at the stage of construction of the complex, and effects in the field of operation of individual buildings and structures for the period of the calculation horizon.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2021 Brest State Technical University
This work is licensed under a Creative Commons Attribution-NonCommercial 4.0 International License.
The work is provided under the terms of Creative Commons public license Attribution-NonCommercial 4.0 International (CC BY-NC 4.0). This license allows an unlimited number of persons to reproduce and share the Licensed Material in all media and formats. Any use of the Licensed Material shall contain an identification of its Creator(s) and must be for non-commercial purposes only. Users may not prevent other individuals from taking any actions allowed by the license.